Loading...
Winning a bid
If your bid was accepted, the next step for larger onsite system installation jobs may be construction planning and staging (typically within a month of starting construction of the system) and then job scheduling (within a few days of start of construction). Construction planning and staging starts after the bid is won and the first payment is secured (if applicable). This stage is usually accomplished at the office within a month of the start of construction. Construction staging is the term that is used to plan how to handle the elements of the site to accomplish the installation of the onsite
Please login or register to view Pumper articles. It's free, fast and easy!
Harkins And Hill
Next ›› How Being Too Busy Can Be Bad Business

Related