Construction planning and staging starts after the bid is won and the first payment is secured (if applicable). This stage is usually accomplished at the office within a month of the start of construction. Construction staging is the term that is used to plan how to handle the elements of the site to accomplish the installation of the onsite
System Site Plans: Next Steps After You Win a Bid
After getting the job, begin these final preparations to ensure the septic installation goes smoothly
Jul 28, 2022 | by Sara Heger, Ph.D. |