Infiltrator Water Technologies Case Study
MBR system enables development of reclaimed strip mine property
Chamber system enables expansion of state park treatment system Problem: A remote location, the need for minimal site impact, and restricted funding challenged wastewater system designers for the Raven Rock State Park in Harnett County, North Carolina. Adding nine new campsites, six RV hookups and a bathhouse required the installation of a 2,655 gpd system and the contractor, Creech’s Plumbing, recommended Quick4 Plus Standard Chambers from Infiltrator Water Technologies to alleviate transportation and storage issues and expedite installation. Chambers were delivered on one truck and hand-carried to the installation site. Solution: A 3% slope allowed use of a gravity flow system to